One manual, the whole season: what ships, on what substrate, through which reviews, from which factories, by when. If a decision isn’t written here, it isn’t made.
01
Season calendar
six milestones · one season
M1Season kickoff — scope + categories locked✓ Feb 09
A press check is a conversation between this page and the sheet. When both agree, sign it. When they don’t, the page wins.
07
Preflight bench
run a vendor file against the rules
Pick a file — the bench runs section 06’s rules and prints the verdict.
08
Capacity & season health
demand vs capacity · rebalanced weekly
Station
Capacity
W28
W29
W30
W31
W32
W33
Legal
10 files/wk
60%
40%
80%
50%
30%
20%
Proofing
14 files/wk
85%
95%
112%
70%
55%
40%
Translations
8 files/wk
50%
75%
100%
88%
38%
25%
Compliance
9 files/wk
45%
55%
70%
65%
80%
30%
W30 overloads proofing: wholesale sell-in samples and the mailer reroute land in the same week. The rebalance, decided Monday: hangtag v7 reproof pulled forward to W29 and the mailer proof moved to Kite’s desk — W30 lands at 96% and the press date never moved.
On-time delivery
95.4%
season to date · target 95.0
Rework
2.8%
of releases · last season 4.6
First-pass preflight
31%
clean on arrival · see the bench
Proof cycles
1.4
per asset · target ≤ 1.5
Surfaced this week — risk, impact, decision
Rust-on-kraft repull (ΔE 3.1) puts M5 drawdown approvals at risk. Second pull scheduled W29; if it misses again, the substrate changes, not the tolerance.
Kite converting runs tight W30–31 (regional holiday). Mailer volume shifted to Alderline: cost +4%, press date held. Decision logged with the program lead.
The board is rebalanced every Monday. Every tradeoff above was written down the day it was made.